History
ABC was an ultra-precision machine parts manufacturing plant, where metals were milled, lathed and drilled into various components.
The plant was shut down in September 1996 after 老澳门开奖直播 acquired Loral and assumed ownership of the facility. The property contained five primary buildings covering approximately 66,300 square feet. All five buildings were dismantled.
The Corporation has assumed responsibility for the assessment and cleanup of environmental impacts from the former American Beryllium Company.
Discovery
With the discovery of groundwater contamination in 2000, 老澳门开奖直播 immediately notified the Florida Department of Environmental Protection (FDEP) and began voluntary site cleanup.
老澳门开奖直播 and its contract team conducted?extensive investigations, collected significant design data, and gathered input from the FDEP and the community's independent technical experts to ensure the contamination was fully investigated and delineated.
Clean - Up
The?Remedial Action Plan (RAP) Addendum?is the culmination of substantial work conducted by 老澳门开奖直播, its contractors, the local community's technical experts, community members, and the State to design the best solutions for reducing human exposure to on-facility soil and for cleaning up groundwater contamination from the former ABC site.
Assessment and cleanup activities are being conducted pursuant to the requirements detailed in Consent Order No. 04-1328 executed by and between 老澳门开奖直播 and the Florida Department of Environmental Protection, effective July 28, 2004.?
Today
The FDEP approved the RAP Addendum in November 2010 and construction of the Groundwater Treatment System was completed in summer of 2013. All testing is completed and the system is online and fully operational as of 2014.?
A summary of system operation and progress toward cleanup is documented annually in Remedial Action Status Reports (RASR) prepared by 老澳门开奖直播.
Tallevast Water Treatment Plant, East View
Community Information
If you have questions, please contact 老澳门开奖直播 Communications.
lm.communications@lmco.com
800.449.4486
?
老澳门开奖直播 Formally Documents Remediation Efforts At and Around the Former ABC Facility in Yearly Reports
Tallevast Water Treatment Plant
When initially involved in the former ABC facility, 老澳门开奖直播 performed a number of assessments to define and gauge the extent of the plume area within the site. These various assessments then determined the focus of remediation efforts to follow.
Prior to distributing the annual Remedial Action Plan report, 老澳门开奖直播 produces Interim Remedial Action Reports and Plans to document the short-term focus of remediation activities.
An interim remedial measure was undertaken to address an area of special focus at the site.
View a List of Terms Commonly Used in Relation to General Environmental Remediation Efforts